Hi Viplove,

 

Still i m not getting any data. I have used both approach.

 

Odata service gives me data in success function module.

 

 

Thanks

Nishant


Re: Progress Analysis Report not showing BCWS and BCWP in CNE5

$
0
0

Hi Faizan

 

 

There are few steps to check ur EVM :

 

1. Ensure default method or assigned method of each object

2. Maintain consistency for EV basis and data >> if you decide to use Annual Cost Plan in your EV version then make sure each object (WBS,Actvity) has annual cost plan value.

3. To ensure POC is calculated, check schedule within activity and related settings

3. Check all parameters through SE38 program CHECKREPORT_PROGRESSANALYSIS

4. Running CNE1

5. Show EV project with PS Profile SAPPS_EV0001

 

note :

+ EV Basis Budget only work in WBS

+ for Internal activity :
   + Plan method : Cost Proportion and Milestone

   + Actual method : Work and Milestone

 

Below is screenshot of my example

4.png

As you can see, there are several key elements shown :

- POC (both planned for BCWS and actual for BCWP)

- Planned Cost (as i use Annual Cost plan as basis)

 

salam hangat,

 

danniel

Mail Notification to a user once payment is approved

$
0
0

Hi Team ,

 

Any user exit to send the mail notification to user once payment is fully approved.

 

As per the standard  SAP BCM workflow the mail notification is being triggered

to the initiator(Any other option to trigger the mail).

 

 

 

Regards

Dwity Krushna Panda

Travel management to WBS standard integration without Fund Management

$
0
0

Dear All,

 

We are facing issue in travel management for below given standard scenarios.

We want to book travel cost/ expenses against WBS. Cost object will be a WBS. The respective WBS will have budget & plan values for the year of posting. We have not implemented fund management and would be unable to do so.


Now the issue is

  1. When trip request is generated & approved, it is not updating estimated travel cost as commitment against a respective WBS budget
  2. When trip is getting settled still the commitment is not getting updated
  3. If a trip is modified/deleted and saved, the committed amount is not getting modified / updated accordingly.
  4. When we post trip cost to finance that time if budget is exceeded system is not allowing it to post which is correct. But till the time of FI posting, there is no information on commitment or probable consumption of budget due to trip cost.


Isn't budgeting, Commitment update and availability controls all standard scenarios in project system.

Shouldn't it also work for any expenses booking scenarios for travel management.



Please advise.


Regards,

Rijuraj

Re: Service PR in ECC can not be created as SRM Local PO

$
0
0

Hi, Vinita


    Thanks your reply, but no service PR is right to create  SRM local PO,  just  issue is for service PR to create PO




   Jesse.

Re: Why are parts of my navigation shown in Contextual Navigation Panel?

$
0
0

Hey Lutz

 

I'd just like to add the following as I accidentally omitted it from my first response.

 

In AFP, workcenter roles are displayed in Contextual Navigation Panel (CNP) view which have only two levels,

 

  • So items on the same level as leaf folder with related services are shown in the Services area.

 

Could you kindly try the following: Go to Detailed Navigation iView. For property 'Navigation Panel Mode' Select 'Always Use Detailed Navigation iView' to display workcenter roles in the Detailed Navigation view.

 

With this enhancement workcenter roles should in theory be displayed with Detailed Navigation view.

 

Many thanks.

 

Kind Regards & Talk Soon

Troy Cronin - Enterprise Portal Support Engineer

Re: Dump in Customs Declaration due to duplicate partner function

$
0
0

Hi Kul,

 

I am not very familiar with the system. Still I tried to find out using BP transaction. I didn't find any duplicate entry in the below screenshot under the 'Partner' tab. Does that mean no duplicate mapping?

 

As for dump, I've to request that from my functional since issue is in production system and he's in a different time zone.

 

 

Capture.PNG

 

Thanks,

Sarif

SAP B1 Distribution rules How-to guide

$
0
0

Could someone point me in the direction of a user guide for SAP B1 9.0 distribution rules?  I would like to know how to set them up, what the options are, what the results might be, how to run them etc.  Regards  Edward


Re: Authorization Control in PM Order

$
0
0
  • In fact, my reply was awaiting your full specifications.
  • However, I was hinting at use of user-exit IWO10009 using a Ztable.
  • This ztable will contain users vs allowed fields
  • And the code in the exit will check whether the logged-in user is editing the field he is allowed for?
  • IF not it will throw an error and the Order is prevented from update.

Re: Is it possible to setup approval process for production order

$
0
0

Hi,

 

There is no way set for approval process for Production order, Receipt from production and Issue for production.

 

Thanks,

Harshal

Re: Service PR in ECC can not be created as SRM Local PO

$
0
0

Hi, Wendy

 

    I think your advice is very useful ,  I will have a try to create a local service PO.

 

   Thanks

 

    Jesse.

Re: Tranport groups in STMS

$
0
0

Hi Chowdary

 

Transport group related to you have many clients in Each SID ( QAS , PRD )

Re: SAP personas 3.0 and IE 11

$
0
0

Hi Pradeep,

 

Our UR team is always looking for web browser changes and testing with our software. The notes I pointed out in my first reply are updated when necessary.

 

Cheers,

Cris

Re: Mulitple workmodes

$
0
0

OK thanks Kenny.
Yes, I see the same issue with "In Process" work modes.

 

However, if I delete the "In Process" work mode, then technical monitoring will stop.
This causes an additional headache for me as I've configured work modes for every part of the day.
E.g:
Non-business: 00:01 - 08:59
Normal business hours: 09:00 - 18:00

Non-business: 18:01 - 23:59

 

So, I've found that I can simply adjust the end-time of the "In Process" work mode, to create a gap (only needs 1 minute gap), into which I can then create a 1 minute downtime work mode, then "Add Phase" to the downtime work mode to extend it accordingly.

The additional phase extends over any other scheduled work modes (as you've found).

 

So I don't lose any monitoring in the time between the current "In Process" work mode and the start of the downtime work mode.

 

Darryl

Re: Insert function in title (text field)?

$
0
0

I can only find the INCIDENT.DATE_LOGGED.

 

here is the query:

 

SELECT

    INCIDENT_ID,

    COUNT(ACT_TYPE_ID) - (SELECT COUNT(*) FROM act_reg a2 WHERE act_reg.incident_id = a2.incident_id AND act_type_id = 6) AS ZUWEISUNGEN

  FROM

    ACT_REG

  WHERE

    ACT_TYPE_ID = 1 AND

    (ACT_REG.ASSYST_USR_ID != '473' or ACT_REG.ASSYST_USR_ID != '712' or ACT_REG.ASSYST_USR_ID != '323' or ACT_REG.ASSYST_USR_ID != '780') AND

    ACT_REG.SERV_DEPT_ID = 28 AND

    ACT_REG.***_SVD_ID <> 28 AND

    INCIDENT_ID IN (

      SELECT

        INCIDENT.INCIDENT_ID

      FROM

        INCIDENT

      LEFT OUTER JOIN INC_DATA ON

        INCIDENT.INCIDENT_ID = INC_DATA.INCIDENT_ID

      WHERE

        INCIDENT.DATE_LOGGED BETWEEN add_months((last_day(SYSDATE))+1,-6) AND add_months((last_day(SYSDATE))+1,-1) AND

        (CSG_ID = '1' OR CSG_ID = '7') AND

        INC_DATA.EVENT_TYPE = 'i' AND

        (INCIDENT.INC_STATUS = 'c' OR INCIDENT.INC_STATUS = 'p')

    )

GROUP BY INCIDENT_ID

ORDER BY ZUWEISUNGEN ASC

 

So the query returns only two fields in CR, which are INCIDENT_ID and ZUWEISUNGEN.

 

Sorry for bothering you so much!!!


Re: Possible to show self-monitoring-alerts in system-alerts ?

$
0
0

HI,

 

Please can you let me know the SP level you are on it is coming for me.

 

I had created a new query.

 

techmon2.PNG

 

I had gone to technical monitoring- > Alert inbox define new query.

 

Thanks

Rishav

Missing authorization and CRM-ECC role issue

$
0
0

Hello Experts,

 

 

 

I have two queries related to Security:

1) I have a scenario where under SU53  screen shot, under S_Develop Auth Obj., I can find 5 fields as

(Missing Authorization)

ACTVT : 03

DEVCLASS: <Dummy>

OBJNAME: <Dummy>

OBJTYPE: DEBUG

P_GROUP:<Dummy>

 

 

When I checked the specific Authorization object under specific Role, I found entries as below:

ACTVT : 03

DEVCLASS: CRM*

OBJNAME: CRM*

OBJTYPE: WAPA

P_GROUP: *

 

 

Now, what are my options here to fix this issue. I need to *** DEBUG Object type, if I add I need to delete the existing one and if I just add without deleting the existing one, the ACTVT field will become same for Object type DEBUG and WAPA. What if I don't want to play with current OBJTYPE type and just add the OBJTYPE DEBUG and its ACTVT? Please suggest.

 

 

 

2) I see that there are roles which are only there in ECC system, not there in CRM. However when we are not able to use a specific transaction in CRM, we make those changes in ECC system. My concern here, if a role is functioning fine in ECC system but when trying the same thing from CRM system(User is there in both systems), it won't work. What could be cause?

 

 

 

 

 

Regards

Piyush

Re: can't create a BOPF-Object

$
0
0

Hi Michael,

 

Please look at the thread below. The solution is provided there. You might need to implement 2 Notes. Let me know if the issue persists even after implementing the note.

 

Use BOPF with ABAP in Eclipse?

 

Thanks and Regards,

Shyam

Re: While making production order

$
0
0

Dear

           Means Batch or stock already assigned with SO through 412 E.

Plz check through MB51.

Re: NF-e não obrigatória na inclusão da MIRO

$
0
0

Leandro, essa nota 1840188 é aplicavel no meu ambiente. Irei aplicar agora e lhe informo.